The hydrogen refueling station in Rothenburg is swiss wide the second hydrogen refueling station from AGROLA. This was also realised in conjunction with the H2Haul project, which is an EU-funded project that aims to deploy 16 zero-emission fuel cell trucks at four sites until 2026.

Main Specifications

Manufacturer: Maximator
Refueling type: 350 & 700 bar (PKW & LKW) parallel
H2-Storage: 350 bar containers (Hydrospider)
Back-to-back capacity: 12 cars / 6 trucks
Space: ~140m² (incl. container storage, without dispenser)

Services provided by H2 Energy AG

  • First greenfield project of an H2 refueling station incl. construction as client & owner
  • Customised financing model for H2 Haul project
  • Evaluation of possible suppliers of H2 fueling station equipment
  • Evaluation of technical and economic aspects across the entire production and supply chain
  • Support during the preparation of the planning application, detailed planning, commissioning.

General Services H2 Energy – a reliable, experienced partner

  • Feasibility study for an H2 refueling station: Site analysis, preliminary clarifications with authorities, installation concept, rough profitability analysis & schedule
  • Preparation of planning application: Elaboration or control of installation plan (area, access, ex-zones)
  • Implementation planning: Collaboration/support in obtaining quotations, ordering H2 fueling station components, planning on-site work
  • Installation & commissioning: Supporting the site management / client with the delivery and installation of the H2 components, commissioning, certification and acceptance

Other Projects

HRS projects in which H2 Energy was involved in a similar way:

  • AVIA: Gossau (St. Gallen)
  • Schwab-Guillod: Müntschemier
  • Coop: Bern
  • Coop: Crissier
  • Coop: Frenkendorf
  • AVIA: Puidoux
  • SOCAR: Grauholz
  • AVIA: Pratteln
  • Oeltrans (in planning): Uetendorf